Day 512 - Update

Thursday, November 30 - Since we last checked in with Ken and Dave...

The Thursday pour has been delayed due to the temperatures. The mornings have been running between 17 and 24 degrees.

Dave and John continue working on the window sill tile. And, after a discussion with Dave, we decided to pull up the entire master bathroom shower pan, reslope it, and retile. Kelli called in an order for more tile. The tile should be in Redding on Friday.

Our master bed frame was delivered on Wednesday. The mattress should be here Monday.

The order has been placed to switch our phone service from the cabin over to the new house. Hopefully, TDS will be able to do the changeover before Monday.

The painters were onsite today, "hard at it" according to Dave. He said that the front door got its undercoat today and that the effect is amazing. Tomorrow, Donn will be out to do all the faux painting. Darn... of all the weeks to miss.

Kelli has been busy shopping for the house. Now we are just short a "few" pieces of furniture.

 