Wednesday, October 4 -- The first rain of the season started at about 5 a.m. this morning. The crew tarped the soil, silt, and bark pile to prevent a real mess...

The rain kept us inside doing dry projects. John continued with the kitchen recess...

Dave installed the toe kick rope light in the master bath. Isn't this SO cool?! That project took until after lunch and uses some pretty creative techniques. He also installed the last closet light and installed hot water recirculation buttons at the wet bar and right sink in the master bath...

Kelli spent most of the day working on the master shower pan grout problem. She is about 3/4 done. Then she created mockups of two possible tile sizes for the kitchen...

The latest view of the log house...

We have had a nice .28" of rain today.