Day 428 - Interior Stairs #4
Thursday , July 27 -- John arrived
about 10:30 again and got the staircase put back together by day's end.
When I left the site at 5:00 p.m., all the treads were on and John was
going to remove the lower set of treads, after getting some dinner, and
prep for the final finish coats. He will put the tread back on tomorrow
morning.
Pictures from throughout the day...

Grain closeup...

The Pete and John team returned. They are REALLY looking forward to
getting the stone done...

Dave took another day off, so connecting the attic air conditioners
will have to wait until tomorrow.
The Walgamuth crew came up to continue repainting after the drywall
mess. Each time they leave, the drywall nightmare fades a little. Gary
at work...

Ken took advantage of our county airport manager, Steve Roberts, being
in the area today and brought him over to talk about the safety barrier
needed along tall retaining wall and the hangar concrete apron. We need
to get Steve a proposal by mid week.
Jason, from BeeBee's water systems, had an appointment cancellation
so came up to finish our installation. He fixed a couple of leak, adjusted
the system, tested the water inside and out, and showed me how the system
works.