Day 428 - Interior Stairs #4

Thursday , July 27 -- John arrived about 10:30 again and got the staircase put back together by day's end. When I left the site at 5:00 p.m., all the treads were on and John was going to remove the lower set of treads, after getting some dinner, and prep for the final finish coats. He will put the tread back on tomorrow morning.

Pictures from throughout the day...

 

Grain closeup...

The Pete and John team returned. They are REALLY looking forward to getting the stone done...

Dave took another day off, so connecting the attic air conditioners will have to wait until tomorrow.

The Walgamuth crew came up to continue repainting after the drywall mess. Each time they leave, the drywall nightmare fades a little. Gary at work...

Ken took advantage of our county airport manager, Steve Roberts, being in the area today and brought him over to talk about the safety barrier needed along tall retaining wall and the hangar concrete apron. We need to get Steve a proposal by mid week.

Jason, from BeeBee's water systems, had an appointment cancellation so came up to finish our installation. He fixed a couple of leak, adjusted the system, tested the water inside and out, and showed me how the system works.